ARTICLE 2. Conditions to Enforcing a Lien [8410. - 8424.]
Article 2 added by Stats. 2010, Ch. 697, Sec. 20.
§§ 8410–8424 · 6 sections
- § 8410 A claimant may enforce a lien only if the claimant has given preliminary notice to the extent required by Chapter 2 (commencing with Section 8200) and made…
- § 8412 A direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the…
- § 8414 A claimant other than a direct contractor may not enforce a lien unless the claimant records a claim of lien within the following times: (a) After the claimant…
- § 8416 (a) A claim of mechanics lien shall be a written statement, signed and verified by the claimant, containing all of the following: (1) A statement of the…
- § 8422 (a) Except as provided in subdivisions (b) and (c), erroneous information contained in a claim of lien relating to the claimant’s demand, credits and offsets…
- § 8424 (a) An owner of real property or an owner of any interest in real property subject to a recorded claim of lien, or a direct contractor or subcontractor…