- § 9300 (a) Except as otherwise provided by statute, before giving a stop payment notice or asserting a claim against a payment bond, a claimant shall give preliminary…
- § 9302 (a) Except as provided in subdivision (b), preliminary notice shall be given in compliance with the requirements of Chapter 2 (commencing with Section 8100) of…
- § 9303 The preliminary notice shall comply with the requirements of Section 8102, and shall also include: (a) A general description of the work to be provided. (b) An…
- § 9304 A claimant may give a stop payment notice or assert a claim against a payment bond only for work provided within 20 days before giving preliminary notice and…
- § 9306 If the contract of any subcontractor on a particular work of improvement provides for payment to the subcontractor of more than four hundred dollars ($400),…