ARTICLE 3. Stop Work Notice
Article 3 added by Stats. 2010, Ch. 697, Sec. 20.
§§ 8830–8848 · 10 sections
- § 8830 “Stop work notice” means notice given under this article by a direct contractor to an owner that the contractor will stop work if the amount owed the…
- § 8832 If a direct contractor is not paid the amount due pursuant to a written contract within 35 days after the date payment is due under the contract, and there is…
- § 8834 A direct contractor that gives an owner a stop work notice shall give the following additional notice: (a) At least five days before giving the stop work…
- § 8836 Within five days after receipt of a stop work notice from a direct contractor, the owner shall give a copy of the notice to the construction lender, if any.…
- § 8838 (a) The direct contractor or the direct contractor’s surety, or a subcontractor or a subcontractor’s surety, is not liable for delay or damage that the owner…
- § 8840 On resolution of the claim in the stop work notice or the direct contractor’s cancellation of the stop work notice, the contractor shall post, and give…
- § 8842 A direct contractor’s right to stop work under this article is in addition to other rights the direct contractor may have under the law.
- § 8844 (a) If payment of the amount claimed is not made within 10 days after a stop work notice is given, the direct contractor, the direct contractor’s surety, or an…
- § 8846 It is against public policy to waive the provisions of this article by contract.
- § 8848 (a) This article applies to a contract entered into on or after January 1, 1999. (b) This article does not apply to a retention withheld by a lender pursuant…