CHAPTER 4. Permits and Fees
Chapter 4 added by Stats. 1967, Ch. 1056.
§§ 18500–18518 · 22 sections
- § 18500 It is unlawful for any person to do any of the following unless he or she has a valid permit issued by the enforcement agency: (a) Construct a park. (b)…
- § 18500.5 Notwithstanding Section 18500, the owner of one manufactured home or mobilehome who is also the owner of the land upon which the manufactured home or…
- § 18500.6 Notwithstanding Section 18500, the owner of a manufactured home or mobilehome who is not a mobilehome park operator and who rents or leases the land upon which…
- § 18501 Applications for a permit to construct or reconstruct shall be accompanied by: (a) A description of the grounds. (b) Plans and specifications of the proposed…
- § 18502 Fees as applicable shall be submitted for permits, as follows: (a) Fees for a permit to conduct any construction subject to this part as determined by the…
- § 18502.5 (a) There is hereby established in the State Treasury the Mobilehome Parks and Special Occupancy Parks Revolving Fund into which funds collected by the…
- § 18503 The department by administrative rule and regulation shall establish a schedule of fees relating to all construction, mechanical, electrical, plumbing, and…
- § 18504 Any person responsible for obtaining any of the permits required by this chapter, Chapter 5 (commencing with Section 18600), or the regulations adopted…
- § 18505 A permit to operate shall be issued by the department following notification by the local enforcement agency of completion of construction of a new park or…
- § 18506 A permit to operate shall be issued by the enforcement agency. A copy of each permit to operate shall be forwarded to the department. A permit to operate shall…
- § 18507 (a) The enforcement agency shall be notified by the new owner or operator of any park of any change in the name or ownership or possession thereof. The notice…
- § 18508 Permits for construction and operation shall be posted in a conspicuous place.
- § 18509 All permits as required in this chapter for construction or reconstruction shall automatically expire within six months from the date of issuance thereof in…
- § 18510 If any person who holds a permit to operate violates the permit or this part, the permit may be suspended by the enforcement agency. This section does not,…
- § 18511 The enforcement agency shall issue and serve upon the permittee a notice setting forth in what respect the provisions of the permit or this code have been…
- § 18512 The notice shall be served by posting at least one copy in a conspicuous place on the premises described in the said permit, and by sending another copy by…
- § 18513 Any permittee receiving a notice issued pursuant to Section 18511 may request and shall be granted a hearing on the matter before an authorized representative…
- § 18514 Upon receipt of such petition the enforcement agency shall set a time and place for such hearing and shall give the petitioner written notice thereof. At such…
- § 18515 Such hearing shall be commenced not later than 10 days after the day on which such petition was filed. Upon application of the petitioner the enforcement…
- § 18516 After such hearing the enforcement agency shall sustain, modify or withdraw the notice, depending upon its findings as to whether the provisions of this part…
- § 18517 If the requirements of the said notice have not been complied with on or before the expiration of 30 days after the mailing and posting of the notice, the…
- § 18518 Upon compliance by the permittee with the provisions of this part and of the notice, and submission of proof thereof to the enforcement agency, the enforcement…