ARTICLE 1.1. Construction Manager/General Contractor Procurement Method for the Department of Water Resources [10112. - 10112.10.]
Article 1.1 added by Stats. 2021, Ch. 247, Sec. 1.
§§ 10112–10112.10 · 11 sections
- § 10112 (a) This article provides for an alternative procurement procedure for certain projects performed by the Department of Water Resources. (b) (1) It is the…
- § 10112.1 As used in this article: (a) “Construction manager” means a partnership, corporation, or other legal entity that is a licensed contractor pursuant to Chapter 9…
- § 10112.2 (a) The Construction Manager/General Contractor method provided by this article may be used by the department, but is not limited to, when it is anticipated…
- § 10112.3 Construction Manager/General Contractor method projects shall progress as follows: (a) (1) The department shall establish a procedure for the evaluation and…
- § 10112.4 (a) Any construction manager that is selected to construct a project pursuant to this article shall possess or obtain sufficient bonding to cover the contract…
- § 10112.5 All subcontractors bidding on contracts pursuant to this article shall be afforded the protections contained in Chapter 4 (commencing with Section 4100) of…
- § 10112.6 The department may retain the services of a design professional or construction project manager, or both, throughout the course of the project in order to…
- § 10112.7 A contract awarded pursuant to this article before it is repealed on January 1, 2033, shall continue in full force and effect until completion, including any…
- § 10112.8 Nothing in this article is intended to affect, expand, alter, or limit any rights or remedies otherwise available at law.
- § 10112.9 (a) The department shall prepare and submit to the Legislature an interim report no later than July 1, 2025, that describes each Construction Manager/General…
- § 10112.10 (a) The authority to perform water resources projects pursuant to this article is for no more than seven projects. (b) This article shall remain in effect…