ARTICLE 3.6. Counties of 500,000 or Less Population [20150. - 20150.14.]
Heading of Article 3.6 amended by Stats. 1984, Ch. 1128, Sec. 9.
§§ 20150–20150.14 · 15 sections
- § 20150 The provisions of this article shall apply to contracts by counties of 500,000 or less population as provided for in Part 2 (commencing with Section 25000) of…
- § 20150.1 (a) Notwithstanding any other law, except as provided in subdivision (b) or (c), every county, whether general law or charter, containing a population of less…
- § 20150.2 As used in this article, “public project” means: (a) A project for the erection, improvement, and repair of public buildings and works. (b) Work in or about…
- § 20150.3 Expenditures for public projects shall not include the costs of: (a) Equipment, supplies and materials acquired by a public agency to enable the timely…
- § 20150.4 Public projects between four thousand dollars ($4,000) and ten thousand dollars ($10,000) shall be let to contract by informal or formal bidding procedures.…
- § 20150.5 Each county shall adopt ordinances or regulations providing for formal and informal bidding procedures as required by this article for public projects…
- § 20150.6 Ordinances or regulations establishing informal bidding procedures shall provide that the county shall, as soon as is practicable after the time for the…
- § 20150.7 The notice inviting informal bids shall be by published notice and may, in addition, be supplemented by mailed notice to contractors registered pursuant to…
- § 20150.8 The notices inviting formal bids shall state the time and place for the receiving and opening of sealed bids and distinctly state the project to be done. The…
- § 20150.9 In its discretion, the county may reject any bids presented. If, after the first invitation for bids, all bids are rejected, after reevaluating its cost…
- § 20150.10 Notwithstanding the provisions of Section 20150.9, on any project which is less than seventy-five thousand dollars ($75,000), if, after the first invitation…
- § 20150.11 It shall be unlawful to split or separate into smaller work orders or projects any public project for the purpose of evading the provisions of this article…
- § 20150.12 The board of supervisors of the county shall adopt plans, specifications, and working details for all public projects the expenditure for which exceeds ten…
- § 20150.13 All bidders on public projects which exceed ten thousand dollars ($10,000) in cost, shall be afforded the opportunity to examine the plans, specifications, and…
- § 20150.14 The provisions of this article shall not apply to the construction of any public building used for facilities of juvenile forestry camps or juvenile homes,…