ARTICLE 29. Public Entities—Municipal Improvement Act of 1913 [20480. - 20497.]
Heading of Article 29 amended by Stats. 1984, Ch. 1128, Sec. 37.
§§ 20480–20497 · 15 sections
- § 20480 The provisions of this article shall apply to contracts by cities, cities and counties, or counties, or other entities, public corporations, or agencies…
- § 20481 At any time after the preliminary approval of the report provided for in Section 10300 of the Streets and Highways Code, the legislative body may let the…
- § 20482 Each contract shall be let to the lowest responsible bidder after notice inviting sealed proposals is published pursuant to Section 6066 of the Government Code…
- § 20483 (a)All bids for construction work shall be presented under sealed cover and shall be accompanied by one of the following forms of bidder’s security which…
- § 20484 Notice of award of the contract shall be published by the clerk of the legislative body once in the newspaper in which the notice of improvement was published.
- § 20485 The owners of three-fourths of the area of lands assessed or liable to be assessed, or their agents (who shall make oath that they are such owners or agents),…
- § 20486 If the owners fail to elect to take the work and to enter into a written contract therefor within 10 days, or to commence the work within 15 days after the…
- § 20487 If, in the opinion of the legislative body, the public interest will not be served by allowing the property owners to take a contract, it may so provide in the…
- § 20488 The contract shall provide that the work shall be done strictly in accordance with the plans and specifications contained in the report provided for in…
- § 20489 The provisions of the Improvement Act of 1911 relating to liquidated damages are incorporated in this division.
- § 20490 If the contractor abandons the work, or fails to proceed with the work as rapidly as required by his contract, the legislative body may declare him in default…
- § 20491 At any time within 10 days after the award of any contract pursuant to this chapter, or if no bids are received, at any time within 10 days after the time…
- § 20492 If the work is abandoned by the city before work is actually started or before any materials, supplies or equipment have been furnished or used, the incidental…
- § 20496 The provisions of Title 3 (commencing with Section 9000) of Part 6 of Division 4 of the Civil Code are hereby expressly made applicable to the construction of…
- § 20497 If in the opinion of the legislative body the public interest will not be served by allowing the property owners to take the contract it may so provide in the…