ARTICLE 5. Certification of Facilities [25794. - 25794.10.]
Article 5 added by Stats. 2022, Ch. 61, Sec. 6.
§§ 25794–25794.10 · 11 sections
- § 25794 For purposes of this article, the following definitions apply: (a) “Department” means the Department of Water Resources or a person designated by the…
- § 25794.1 (a) Notwithstanding any other law, from October 31, 2022, to October 31, 2026, inclusive, the department shall submit an application for certification to the…
- § 25794.2 (a) The commission shall establish a process to expedite review of an application submitted pursuant to this article. The process shall include guidance to the…
- § 25794.3 Upon receipt of an application pursuant to this article, commission staff shall establish a docket for the proceeding and publish a notice of receipt and shall…
- § 25794.4 (a) Within 20 days of the submission of the application pursuant to this article, the executive director shall review the application for completeness. The…
- § 25794.5 Upon an application being deemed complete, the commission shall do all of the following: (a) (1) Comply with subdivisions (d) to (g), inclusive, of, and…
- § 25794.6 The commission shall not certify a site and related facility if any of the following applies: (a) The site is a site described in Section 25527. (b) The site…
- § 25794.7 The commission shall maintain on its internet website a list of all certifications granted pursuant to this article for as long as the certifications are in…
- § 25794.8 (a) A certificate issued pursuant to this article shall be valid for a period not to exceed five years from the date of issuance. (b) If a facility operates…
- § 25794.9 Sections 25532 to 25537, inclusive, apply to a certificate issued pursuant to this article.
- § 25794.10 (a) The executive director shall charge and collect a reasonable fee from the department upon the submittal of an application pursuant to this article to cover…