ARTICLE 2. Interconnection of Facilities
Article 2 added by Stats. 1976, Ch. 915.
§§ 2811–2816 · 6 sections
- § 2811 In order to promote the more efficient use and distribution of natural gas or electric energy and eliminate the necessity for construction of transmission…
- § 2812 Upon application of a private energy producer, and after notice to any affected public utility and hearing thereon, the commission shall authorize such…
- § 2812.5 Upon application of a private energy producer, and after notice to any affected public utility and hearing thereon, the commission shall authorize such…
- § 2813 The private energy producer shall be required to provide and to pay the total cost of the interconnection as well as any costs associated with providing a…
- § 2815 Nothing in this chapter shall require that any private energy producer perform any service or deliver any commodity to the public or any portion thereof, for…
- § 2816 Every public utility shall keep accurate records of transactions with a private energy producer, and of the use of the public utility’s facilities by the…