- § 10250 The department may increase or decrease quantities of work to be done under a unit basis contract during the progress of the work.
- § 10251 The department may cause the insertion of provisions in any contract for the performance of such extra work and the furnishing of materials therefor by the…
- § 10252 The director may grant such extensions of time for completion as he deems for the best interests of the state.
- § 10253 If the director deems that a contractor has failed to supply an adequate working force, or material of proper quality, or has failed to comply with Section…
- § 10254 If the defaults are not remedied within the time specified in the notice, the contractor’s control shall terminate as of the expiration of that time.
- § 10255 Upon such termination, the director may take possession of and use all or any part of the contractor’s materials, tools, equipment, and appliances upon the…
- § 10256 Such informal contracts may be awarded only after a proposal form has been prepared, a copy is served upon the contractor whose control has been terminated,…
- § 10257 The provisions of this part, except as to prequalification, are not applicable to the award of informal contracts.
- § 10258 If the control of a contractor is terminated or he abandons the work, and the work is performed by day’s labor or informal contract as provided in Section…
- § 10259 On the completion of the contract, the original contractor is entitled to the return of all his unused materials, and his equipment, tools, and appliances,…
- § 10260 The notices required by this article may be served on the contractor or on his agent having charge of the work, personally, or by registered mail addressed to…
- § 10261 (a) Payments upon contracts shall be made as the department prescribes upon estimates made and approved by the department, but progress payments shall not be…
- § 10261.5 (a) Any state agency which fails to make any progress payment within 30 days after receipt of the payment request from a contractor on a construction contract…
- § 10261.7 (a) Within 10 days of making a construction contract payment, a state agency that maintains an Internet Web site shall post on its Internet Web site the…
- § 10262 The contractor shall pay to his or her subcontractors, within seven days of receipt of each progress payment, the respective amounts allowed the contractor on…
- § 10262.3 To facilitate enforcement of Section 10262, the Department of General Services shall publish in the California State Contracts Register notice of progress…
- § 10262.5 (a) Notwithstanding any other law, a prime contractor or subcontractor shall pay to any subcontractor, not later than seven days after receipt of each progress…
- § 10263 (a) Provisions shall be included in any invitation for bid and in any contract documents to permit the substitution of securities for any moneys withheld by a…
- § 10264 (a) With the exception of projects over water requiring marine access, and which have a contract amount greater than twenty-five million dollars ($25,000,000),…
- § 10265 A claim pursuant to Part 3 (commencing with Section 900) of Division 3.6 of Title 1 of the Government Code is not required, but legal action on any claim shall…